Two outward channel projects of Guangzhou Port are won by Guangzhou Dredging

Source:Guangzhou DredgingTime:2018-06-21

Recently Guangzhou Dredging has won the bid for two outward channel projects of Guangzhou Port, with a total contract amount of some RMB 760 million.


The maintenance project of the north section of the outward channel of Guangzhou Port has a full length of some 73.15 kilometers, a maintenance period of 7 months and a contract amount of some RMB 88.73 million. Section 4 of the deepwater channel broadening project of Guangzhou Port has a full length of 8.2 kilometers, a construction period of 13 months and a contract amount of some RMB 670 million; apart from channel dredging, 10 lighted buoys in corresponding segments will be repositioned.