Two offshore wind power projects are won consecutively by Third Harbour Engineering

Source:Third Harbour EngineeringTime:2018-05-25

Recently Third Harbour Engineering has won two offshore wind power projects consecutively, with a total contract amount of some RMB 1,600 million.


With a contract amount of RMB 620 million and a construction period of 13 months, CGN's 400MW offshore wind power project on Nanpeng Island, Yangjiang, Guangdong involves the foundation construction and installation of 18 wind turbines and booster station foundation construction. The foundation includes four piles and a jack.


With a contract amount of RMB 953 million and a construction period of 596 days, CDT's 300MW offshore wind farm project in Binhai, Jiangsu Province involves the foundation production and construction of 50 wind turbines, the production and installation of 50 towers and the installation of 50 wind turbines.