300,000T Crude Oil Quay Project in Dalian

Source:Time:2008-07-28

This project consists of main part of quay, trestle and approach embankment. The main part of quay adopts the caisson-gravity-pier quay structure, consists of 1-9# piers and 12 caissons and has a total length of 510m. The trestle employs caisson-gravity-pier trestle quay structure, consists of 10-13# pier and 4 caissons and has total length of 585.45m. The approach embankment's axis is 373.15m in length and mainly includes riprap slope embankment, shore-connecting rest piers, etc.